System installation
at The Museum Of Ancient Life
Thanksgiving Point, Lehi,Utah.
This large format theatre had existed barely two years when the
15/70 3D system that was originally installed in Ontario Mills Mall aquired
and installed. The following photos were taken during installation.
In preperation for installing the 15/70 equipment the booth had to
be made deeper. These "I" beams were added to the flooring supports to
extend the rear wall of the booth out by about 18 inches.
The extended rear wall is shown being put in. This area was primarily
to accomodate passing by the platter systems and keeping within fire codes.
The front projection position for both 15/70 machines. The large projection
port was enlarged from the existing smallish port for the original 8/70
system. Note that the cross beam was cut out to make room for the port.
These cross beams are normally installed in a building as added earthquake
protection. The buildings architect determined it was safe for the
contractor to remove this section of beam.
An electrical extra service was brought in as the projectors have the
usual amount of support gear that demands a larger feed.
Installation begins in ernest at 5:30 am the first Monday after completion
of the booth changes. The first audio rack is brought out of storage and
makes its way up to the front of the Museum where the crane operator is
getting his crane placed and rigged.
The new screen frame and silver screen arrive from MDI in Canada.
The frame was made in relatively small sections and screen installation
people off loaded it by hand, but the crane was required to lift the screen
off the flatbed truck.
Riging the first audio rack for lifting inside the booth. The crane
used had a 175 foot boom as it was quite a long lift out over the roof
to get equipment into the booth.
Up goes the first rack and a quick check for integrity and balance
and it was off...
That crane was really huge...couldn't quite get it all in one shot.
Definitely the easiest way to move in 800 lbs of audio rack.
The contractor only had half the hole cut in the roof when the first
rack arrived upstairs so they took a break while the racks were coming
in.
On this job it all made it safely into the booth. The crane operator
was really good.
Technicians from CDC inspect and unpack the 15/70 platter systems,
and projectors upon arrival.
Projection equipment was off loaded with a fork lift and awaits its
ride into the booth.
The right size hole for the job! This is the projector podium position...the
hole was completely filled with 1/2 and 3/4 inch conduit by the end of
the day.
Incoming Left eye projector/platter control cabinet.
CDC technicians inspect the left eye projector control cabinet after
placement. The quality of construction of the control cabinets is very
evident.
Getting the projector track up on machinery movers and readying it
for both 15/70 projectors.
Determining the proper rigging of the projectors was all handled by
the crane operator and CDC technicians.
When the first machine was lifted slightly off the ground to check
balance there was a huge cracking sound. Note the pallett starting to give
out on the sides from the weight of these 2800 lb monsters.
Up and away...the crane operator had determined all was safe and that
only the side planks on the pallets were giving under the weight of it
all.
Click here to go to page 2